2018, Marshall Av, Napa County
-
Project #:
19512 -
Est. Start Date:
July 2018 -
Est. Completion Date:
September 2020 -
Beginning Location:
2172 Marshall Av -
End Location:
Imola Av -
Section Length:
426' -
Map Cordinates:
38.281222, -122.266392 -
Description of Improvements:
Road Reconstruction and Overlay project on Marshall Av.
-
Total Project Cost
$122,389 -
Spent
$117,403
Phase
- Design
- Construction
- Complete