2022, Oak Knoll Av., Napa County

  • Project #:
    22512
  • Est. Start Date:
    Febraury 2022
  • Est. Completion Date:
    September 2022
  • Beginning Location:
    SR-29
  • End Location:
    Silverado Trail
  • Section Length:
    10,962'
  • Map Cordinates:
    38.353331, -122.331235
  • Description of Improvements:

    Surface Treatment project on Oak Knoll Av. from SR-29 to Silverado Trail.

  • Total Project Cost
    $526,561
  • Spent
    $451,763
Phase
  • Design
  • Construction
  • Complete