close
BACK

2019, Hudson Av., City of St. Helena

  • Project #:
    19567
  • Est. Start Date:
    March 2019
  • Est. Completion Date:
    September 2019
  • Beginning Location:
    Madrona Av
  • End Location:
    Adams St
  • Section Length:
    845'
  • Map Cordinates:
    38.499946, -122.477193
  • Description of Improvements:

    Overlay project on Hudson Av. from Madrona Av. to Adams St.

  • Total Project Cost
    $98,208
  • Spent
    $98,208
Phase
  • Design
  • Construction
  • Complete