2019, Vorhees Cir., City of St. Helena
-
Project #:
19552 -
Est. Start Date:
March 2019 -
Est. Completion Date:
June 2023 -
Beginning Location:
E. Mitchell Dr -
End Location:
W. Mitchell Dr -
Section Length:
915' -
Map Cordinates:
38.499133, -122.470389 -
Description of Improvements:
Overlay project on Vorhees Cir. from E. Mitchell Dr. to W. Mitchell Dr.
-
Total Project Cost
$139,338 -
Spent
$61,301
Phase
- Design
- Construction
- Complete