BACK
2019, Henry Ct, City of St. Helena
-
Project #:
19560 -
Est. Start Date:
March 2019 -
Est. Completion Date:
September 2020 -
Beginning Location:
Park St -
End Location:
End of Henry Ct -
Section Length:
120' -
Map Cordinates:
38.509244, -122.474379 -
Description of Improvements:
Overlay project on Henry Ct. from Park St. to End on E. Henry Ct.
-
Total Project Cost
$18,274 -
Spent
$18,274
Phase
- Design
- Construction
- Complete