2018, Spring St., City of Calistoga

  • Project #:
    19583
  • Est. Start Date:
    October 2018
  • Est. Completion Date:
    Jun 2019
  • Beginning Location:
    Cedar St
  • End Location:
    End of Street
  • Section Length:
    390'
  • Map Cordinates:
    38.577493, -122.581656
  • Description of Improvements:

    Pavement Reconstruction project on Spring St. from Cedar St. to End of Street.

  • Total Project Cost
    $222,611
  • Spent
    $222,611
Phase
  • Design
  • Construction
  • Complete