BACK
2021, S. Washington Street Rehabilitation, Town of Yountville
-
Project #:
21520, 21521, 21522, 21523 -
Est. Start Date:
March 2021 -
Est. Completion Date:
July 2021 -
Beginning Location:
Yount St -
End Location:
Town Limits -
Section Length:
2,832' -
Map Cordinates:
38.401783, -122.360900 -
Description of Improvements:
Rehabilitation project of S. Washington St. from Yount St. to Town Limits. The project encompasses the following street segments:
Project No. 21520: S. Washington St. from Yount St. to Oak Circle.
Project No. 21521: S. Washington St. from Oak Circle to California Dr.
Project No. 21522: S. Washington St. from California Dr. to Champagne.
Project No. 21523: S. Washington St. from Champagne to Town Limits.
-
Total Project Cost
$652,517 -
Spent
$652,517
Phase
- Design
- Construction
- Complete