close
BACK

2019, Dry Creek Rd. – MPM 7.51, Napa County

  • Project #:
    19580
  • Est. Start Date:
    Febraury 2019
  • Est. Completion Date:
    August 2020
  • Section Length:
    280'
  • Description of Improvements:

    Storm Damage Repair and Road Reconstruction project on Dry Creek Rd. at mile-post-marker 7.51.

  • Total Project Cost
    $740,263
  • Spent
    $740,263
Phase
  • Design
  • Construction
  • Complete