2019, Dry Creek Rd. – MPM 7.75, Napa County

  • Project #:
    19576
  • Est. Start Date:
    February 2019
  • Est. Completion Date:
    August 2020
  • Section Length:
    197'
  • Description of Improvements:

    Storm Damage Repair and Road Reconstruction project on Dry Creek Rd at mile-post-marker 7.75.

  • Total Project Cost
    $525,729
  • Spent
    $525,729
Phase
  • Design
  • Construction
  • Complete