close
BACK

2023, Silverado Trail – Petrified Forest Paving, Napa County

  • Project #:
    24502
  • Est. Start Date:
    July 2023
  • Est. Completion Date:
    December 2023
  • Section Length:
    19650'
  • Description of Improvements:

    Overlay paving and asphalt repair project on Silverado Trail, Petrified Forest Rd, Whitehall Ln, Napa County RDS 23-13.

  • Total Project Cost
    $3,553,492
  • Spent
    $2,420,932
Phase
  • Design
  • Construction
  • Complete