BACK
2023, Streets Rehabilitation Microsurfacing, Town of Yountville
-
Project #:
23523, 23524, 23525, 23526 -
Est. Start Date:
TBD -
Est. Completion Date:
TBD -
Section Length:
3,327' -
Description of Improvements:
Rehabilitation project encompasses the following street segments:
Project No. 23523: Finnell Rd. from Hopper Creek Bridge to Town Limits.
Project No. 23524: Heather St. from Mulberry St. to End of Road.
Project No. 23525: Yountville Cross from Yount St. to Town Limits.
Project No. 23526: Yount St from Yountville Cross to Adams St.
-
Total Project Cost
$500,000 -
Spent
$0
Phase
- Design
- Construction
- Complete