2019, Hudson Av., City of St. Helena

  • Project #:
    19568
  • Est. Start Date:
    March 2019
  • Est. Completion Date:
    September 2019
  • Beginning Location:
    Adams St
  • End Location:
    Spring St
  • Section Length:
    870'
  • Map Cordinates:
    38.498525, -122.474068
  • Description of Improvements:

    Overlay project on Hudson Av. from Adams St. to Spring St.

  • Total Project Cost
    $101,114
  • Spent
    $101,114
Phase
  • Design
  • Construction
  • Complete