2018, Parrish Rd., Napa County

  • Project #:
    19513
  • Est. Start Date:
    July 2018
  • Est. Completion Date:
    October 2019
  • Beginning Location:
    Shetler Av
  • End Location:
    Imola Av
  • Section Length:
    939'
  • Map Cordinates:
    38.282684, -122.265553
  • Description of Improvements:

    Road Reconstruction and Overlay project on Parrish Rd. from Shetler Av. to Imola Av.

  • Total Project Cost
    $203,982
  • Spent
    $195,670
Phase
  • Design
  • Construction
  • Complete