2021, Paving Program, City of Napa
-
Project #:
21504 -
Est. Start Date:
July 2021 -
Est. Completion Date:
December 2021 -
Beginning Location:
Various Streets -
Section Length:
14,290' -
Map Cordinates:
38.281540, -122.307100 -
Description of Improvements:
Overlay project on the following Courts: Stiles, Calvary, Clement, Jacqueline, Gordon, Kingford, Caber, Exeter; and Streets: Clifford, St. Francis Cir., Grandview, Hilton, Stallings, Summerfield, Manchester, Hyde Park, Darling.
-
Total Project Cost
$1,485,818 -
Spent
$1,485,818
Phase
- Design
- Construction
- Complete