close
BACK

2021, Paving Program, City of Napa

  • Project #:
    21504
  • Est. Start Date:
    July 2021
  • Est. Completion Date:
    December 2021
  • Beginning Location:
    Various Streets
  • Section Length:
    14,290'
  • Map Cordinates:
    38.281540, -122.307100
  • Description of Improvements:

    Overlay project on the following Courts: Stiles, Calvary, Clement, Jacqueline, Gordon, Kingford, Caber, Exeter; and Streets: Clifford, St. Francis Cir., Grandview, Hilton, Stallings, Summerfield, Manchester, Hyde Park, Darling.

  • Total Project Cost
    $1,485,818
  • Spent
    $1,485,818
Phase
  • Design
  • Construction
  • Complete