2019, Trower Av. Phase 2, City of Napa
-
Project #:
19573 -
Est. Start Date:
June 2019 -
Est. Completion Date:
November 2019 -
Beginning Location:
Jefferson St. -
End Location:
East End (City Limits) -
Section Length:
4,621' -
Map Cordinates:
38.325144, -122.327724 -
Description of Improvements:
Hot Mix Asphalt Grind and Overlay and Concrete Improvements on Trower Ave from Dry Creek Rd to Linda Vista Ave; Hot Mix Asphalt Grind and Overlay with Concrete Curbs, Gutters, Sidewalks and Curb Ramps on Trower Ave from Jefferson St to East End (City Limits); Overlay on Jefferson St from Trower Ave to Sierra Ave.
-
Total Project Cost
$582,391 -
Spent
$516,619
Phase
- Design
- Construction
- Complete